Latest:
From 20th February work will start on removing the Rhododendron and Laurel
through the Grove wood and towards the Blandford Road entrance using chainsaws and a
tractor-mounted flail, and is likely to take
up to two weeks. Some paths & access
may be limited whilst the work is
undertaken.
This approach is
similar to that used in the project at
Longmeadow Lane
Woods between 2008-09.
The removal of these invasive plants will
benefit wildlife and the quality of the
woodland because they make the soil very
acidic and shade out all native plants such
as bramble, nettles, foxgloves and
bluebells.
Following the vegetation clearance the trees
will be assessed for safety and worked on as
necessary. New hedges will be planted and
opportunities will be created for natural
play and enhanced dog walking facilities.
|
Progressing the projects
All
the proposals taken forward to the public consultation were
well received, and in most cases with a clear majority –
see the graph of results, right. We also
received a wealth of individual comments that have been
extremely valuable in shaping the way the project will be
progressed.
This
does not mean that we will be pushing ahead with all of the
ideas on the consultation form. The main theme we took from
responses and from face-to-face discussions was to resist
changing Upton Country Park just for the sake of it. People
like the park as it is and wish us to preserve its
tranquility .
Leisure
Services now intend to undertake various works in two
phases. These works will respect the views of the public
whilst increasing the amount of open space available,
improving the quality of access into and around the park and
allow for the installation of a new interactive trail.
Click on the images (right)
to download plans with an explanation of the works to be
undertaken
Phase 1 (early
2012)
In the first
phase of work three areas, totalling 6.3 hectares (16 acres)
will be made more accessible to the public through the
creation of new entrances and footpaths, the removal of
fence lines, clearance of dense under-storey vegetation and
other infrastructure improvements.
Over the long
term the clearance of non-native vegetation such as Laurel
and Rhododendron will allow the woodland to naturally
regenerate and let in more light, creating a better quality,
more diverse habitat.
Phase 2
The public
consultation revealed strong support for the inclusion of
formal play equipment, natural play (boulders, logs, mounds
and other natural features) and for bespoke seating and
sculpture so long as it is in keeping with the park and
positioned appropriately. These elements will for phase two
of the works and will be fully considered once the Phase 1
has been undertaken in early 2012.
Councillor
Judy Butt,
Cabinet Portfolio Holder for Communities, Public
Engagement and Participation, says: "Upton Country Park
is so popular with local people, being a beautiful open
space to relax and enjoy the great outdoors. I am really
pleased that we can make these new improvements to the
Park in answer to the needs of our local
Poole residents. The new plans will provide greater
interest and participation for all park users, see you
there!”.
Consultation
Between 25th
June - 26th July 2011 we consulted with Park users on:
The zoning
of different activities
Enhanced
cycling routes and facilities
Opportunities for natural & formal play experiences
Designated
areas for dog walkers, such as a dogs off-lead area
Areas for
sport, recreation & events
Retaining
the enjoyment of formal gardens and wildlife areas.
On Saturday,
25th June we met with park users in the car park when they
had an opportunity to consider and respond to the proposals
in person
We then made
an online questionnaire available with the option to
download a copy of our questionnaire to print and post to
us.
The
consultation period for this stage of the project ended 26th
July
A big thank
you to everyone who completed our questionnaire.
We received
approximately 200 paper copies and more than 60 online
responses, which gave us a lot to consider; it took a
considerable amount of time to analyse the results and all
the comments received.
The principle
conclusion is that all our proposals were well received, and
in most cases with a clear majority – see the graph of
results, above right
This does not
mean that we will be pushing ahead with all of the ideas on
the consultation form. The main theme we took from responses
and from face-to-face discussions was to resist changing
Upton Country Park just for the sake of it.
Thank you
again to everyone who completed a questionnaire or who came
along to a consultation event
|
|
 |
|
Click on images to view full size: |
 |
|
The results of the consultation (PDF, 406kb) |
 |
|
Play &
Recreation Enhancements - overview (PDF, 800kb) |
 |
|
Play &
Recreation Enhancements
Detail Map 1,
Ropers Lane (PDF, 300kb) |
|
|
 |
|
www.uptoncountrypark.com |
|