A regularly updated resource for Councillors and residents...

Happening Now

Last Update

Completion due

22 Playbuilder Projects - play area improvements:

 

 
 

~ Six Playbuilder opening events in April, details soon

   
 

~ Five Playbuilder opening events 15th February

   
 

~ Gough Crescent play area to re-open 11th Mar

8th Mar

11th March

 

~ Haskells Rec play area closed from 13th Jan

8th Mar

Mid March

 

~ Oakdale play area new play area under construction

8th Mar

19th March

 

~ Springdale Rec, Lewesdon Drive closed from 12th Feb

10th Mar

End March

 

~ Alexandra Park play plans to go ahead soonest

9th Mar

End April

 

~ All Playbuilder sites - work schedule

 

 

Sandbanks - finishing touches for summer 2010

25th Feb

May 2010

Green Gyms - additional new equipment for Poole Park

26th Feb

March 2010

Oakdale Community Park - access arrangements

27th Jan

End May 2010

Parkstone Park - final plans for improvements

15th Jan

May 2010

Poole Harbour Canoe Club at Poole Park

28th Jan

Spring 2010

Dolphin Sports Centre concourse improvements

28th Jan

Winter 2010/11

Other Leisure Projects Happening Now in brief

9th Dec

 


www.boroughofpoole.com/leisureprojects

www.boroughofpoole.com

Website update notification by email

Site compiled for information purposes only.  Please direct any questions or comments to Sarah Austin, Project Officer