OFFICIALLY
OPENED by local school children on Monday 15th February 2010
The first of
twenty two Poole Playbuilder sites! Installers made an early start at Sherborn
Crescent when a job elsewhere in the country was postponed.
The play area was closed on 28th October and re-opened on a sunny
Saturday, 7th November.
The existing
play equipment has been repainted, and three new items are being
installed - the roundabout, zip wire and jungle climber; we'll
be back to add the finishing touches (seating and a litter bin) by the
end of March.
Misfit
A specially
made 11m 'embankment slide' was supposed to link the upper and lower
levels, and it arrived on 16th November as planned.
Unfortunately it didn't fit the space properly and could have been
dangerous to use so it had to be returned. The money will be
spent other improvements.
10th Nov,
the zip wire with Matta tiles installed to protect against
wear-and-tear
11th Feb;
the invitation goes out for the official opening on Monday
9th Nov, the
new roundabout and repainted climbing frame
10th Nov,
the new jungle climber - installed into green 'Cushionfall'
Unfortunately,
we experienced some problems over the first weekend when the
security fencing was brought down and part of the zip wire was
damaged by fire on Sunday night.
2nd Nov, the zip
wire 'launch pad' suffered fire damage
3rd Nov, the zip
wire (a replacement launch pad has been borrowed from another
project)