A regularly updated resource for Councillors and residents...

Happening Now

Last Update

Completion due

22 Playbuilder Projects - play area improvements:

 

 
 

~ Five Playbuilder opening events 15th February

   
 

~ Uppleby Road play area re-opened

5th Feb

Completed

 

~ Turlin Moor Pavilion play area re-opened

28th Jan

Completed

 

~ Gough Crescent play area closed from 4th Jan

20th Jan

12th Feb

 

~ Haskells Rec play area closed from 13th Jan

20th Jan

12th Feb

 

~ Alexandra Park work to re-commence in February

27th Jan

End March

 

~ Playbuilder work schedule

 

 

Green Gyms - additional new equipment for Poole Park

3rd Feb

March 2010

Oakdale Community Park - access arrangements

27th Jan

End May 2010

Parkstone Park - final plans for improvements

15th Jan

May 2010

Poole Harbour Canoe Club at Poole Park

28th Jan

Spring 2010

Dolphin Sports Centre concourse improvements

28th Jan

Winter 2010/11

Other Leisure Projects Happening Now in brief

9th Dec

 


www.boroughofpoole.com/leisureprojects

www.boroughofpoole.com

Website update notification by email

Site compiled for information purposes only.  Please direct any questions or comments to Sarah Austin, Project Officer

© 2009 Borough of Poole Leisure Services, Greenspace Development Team

Northmead House, 30-32 Northmead Drive, Creekmoor, Poole BH17 7RP